Activities

Completed

Phase 1 – Elaboration of the solution, design and realization of the experimental model, design of the prototype of the system

21.06.2022 – 31.12.2022
(~ 6 months)

Act 1.1 – Study of the existing experimental model and the presentation of the existing constructive solutions on the market in the field of energy storage systems using the flywheel principle

Act 1.2 – Elaboration of the solution for the realization of the prototype of the inertial system for energy storage

Act 1.3 – Optimization study and prototype design of inertial energy storage system

Act 1.4 – Dissemination of information

Completed

Phase 2 – Realization of prototype energy storage system in the flywheel and specific test stand

03.01.2023 – 29.12.2023
(~ 12 months)

Act 2.1 – Design of test stand and work devices

Act 2.2 – Realization of test stand and working devices

Act 2.3 – Realization of a prototype energy storage system in the flywheel

Act 2.4 – Reference development of the energy storage system in the flywheel

Completed

Phase 3 – Prototype testing of the energy storage system in the flywheel

03.01.2024 – 20.06.2024
(~ 6 months)

Act 3.1 – Prototype testing of the energy storage system in the flywheel

Act 3.2 – Functionality demonstration and prototype validation

Act 3.3 – Demonstration of the functionality and validation of the prototype

Act 3.4 – Patents